PTCCAP 2009
PTC Capital Investment Program
 

 
 
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
  Program/Category/Project
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
Meas.Plan
PTCCAP/2009 PTC Capital Investment Program $483,663,000 $421,510,000 $436,090,000 $476,840,000 $475,000,000 $475,000,000 $460,100,000 $460,000,000 $460,000,000 $456,000,000
                       
PTCCAP-01 Highway Program $403,000,000 $348,250,000 $363,800,000 $413,400,000 $412,600,000 $396,000,000 $391,000,000 $402,000,000 $401,000,000 $401,000,000
PTCCAP-01-01 Roadway/Safety Prog $31,675,000 $63,850,000 $48,450,000 $42,280,000 $43,290,000 $42,600,000 $43,100,000 $40,200,000 $40,100,000 $40,100,000
WBS A-049.00R002 Bituminous Overlay MP A49-A59 $1,100,000 $ - $- $- $- $- $- $- $- $-
WBS A-089.00R003 Bituminous Overlay MP A89-A95 $1,600,000 $5,900,000 $- $- $- $- $- $- $- $-
WBS A-105.00R001 Bituminous Overlay MP A105-A110 $500,000 $- $- $- $- $- $- $- $- $-
WBS A-125.00R001 Bituminous Overlay MP A125-A130 $50,000 $1,200,000 $3,300,000 $- $- $- $- $- $- $-
WBS EN-00028 Access Ramp Construction $1,600,000 $2,600,000 $500,000 $- $- $- $- $- $- $-
WBS EN-00029 Concrete Median Barrier Installation-Systemwde $100,000 $3,000,000 $3,000,000 $3,000,000 $2,030,000 $3,000,000 $4,000,000 $- $- $-
WBS EN-00030 Guide Rail End Treatment $- $- $- $- $- $- $- $- $- $-
WBS EN-00033-3 Misc. Bit. Overlay/Roadway/Open End Paving/Drainage - Systemwide $- $50,000 $1,600,000 $9,000,000 $9,000,000 $9,000,000 $9,000,000 $9,000,000 $9,000,000 $9,000,000
WBS EN-00036 Safety Improvements to Wide Areas - Systemwide $400,000 $400,000 $400,000 $- $- $- $- $- $- $-
WBS EN-00039 Mill & Pave Projects - Systemwide $- $- $- $21,330,000 $30,610,000 $27,600,000 $28,600,000 $31,200,000 $31,100,000 $31,100,000
WBS EN-000432007 Misc. Bit. Overlay/Roadway/Open End Paving/Drainage - Systemwide $500,000 $- $- $- $- $- $- $- $- $-
WBS EN-000442008 Misc. Bit. Overlay/Roadway/Open End Paving/Drainage - Systemwide $8,600,000 $- $- $- $- $- $- $- $- $-
WBS EN-00045 Attenuator Replacement at Interchanges - Systemwide $500,000 $500,000 $- $- $- $- $- $- $- $-
WBS EN-00047 Additional Truck Parking $7,300,000 $6,000,000 $1,200,000 $- $- $- $- $- $- $-
WBS EN-000492009 Misc. Bit. Overlay/Roadway/Open End Paving/Drainage - Systemwide $1,500,000 $8,000,000 $- $- $- $- $- $- $- $-
WBS EN-000882010 Miscellaneous Misc. Bit. Overlay/Roadway/Open End Paving/Drainage - Systemwide $50,000 $1,600,000 $8,000,000 $- $- $- $- $- $- $-
WBS EN-00090 Existing Conc. Pavement resealing of joints & repairs -AKH $- $- $- $150,000 $1,500,000 $1,500,000 $- $- $- $-
WBS EN-00091 Existing Conc. Pavement resealing of joints & repairs -AKH $- $- $- $- $150,000 $1,500,000 $1,500,000 $- $- $-
WBS M-030.00R001 Roadway Reconstruction MP M30-M32.4 $100,000 $450,000 $4,150,000 $8,800,000 $- $- $- $- $- $-
WBS T-010.00R001 Bituminous Overlay, MP 10-19 $2,000,000 $12,000,000 $- $- $- $- $- $- $- $-
WBS T-025.00R001 Bituminous Overlay, MP 25-31 $100,000 $2,000,000 $6,000,000 $- $- $- $- $- $- $-
WBS T-031.00R001 Bituminous Overlay, MP 31-42 $10,000 $4,000,000 $- $- $- $- $- $- $- $-
WBS T-048.00R001 Bituminous Overlay, MP 48-57 $100,000 $3,000,000 $8,000,000 $- $- $- $- $- $- $-
WBS T-067.00R001 Bituminous Overlay, MP 67-74 $10,000 $2,500,000 $- $- $- $- $- $- $- $-
WBS T-109.91R001 Somerset Interchange Access Road Improvements $700,000 $2,650,000 $3,800,000 $- $- $- $- $- $- $-
WBS T-193.00R001 Bituminous Overlay, MP 193-199 $3,000,000 $- $- $- $- $- $- $- $- $-
WBS T-255.00R001 Bituminous Overlay, MP 255-263 $5,000 $- $- $- $- $- $- $- $- $-
WBS T-266.00R001 Bituminous Overlay, MP268-275 $1,750,000 $4,500,000 $- $- $- $- $- $- $- $-
WBS T-282.00R001 Bituminous Overlay, MP282-292 $100,000 $3,500,000 $8,500,000 $- $- $- $- $- $- $-
                     
PTCCAP-01-02 Bridge,Tunnels & Misc. Structure $126,690,000 $125,620,000 $80,345,000 $60,450,000 $101,800,000 $85,800,000 $89,800,000 $84,700,000 $104,500,000 $116,700,000
WBS A-030.90S001 Replacement of Mainline Bridge Nos. NB-150, NB-152 $370,000 $- $3,900,000 $9,900,000 $3,900,000 $- $- $- $- $-
WBS A-047.40S001 Replacement of Mainline Bridge No. NB-306 $1,800,000 $3,500,000 $- $- $- $- $- $- $- $-
WBS A-051.36S00 Replacement of Mainline Bridge No. NB-323 $300,000 $300,000 $300,000 $- $- $2,000,000 $6,000,000 $- $- $-
WBS A-057.66S001 Superstructure Replacement of Bridge Nos. NB-355, NB-360, NB-363 $250,000 $300,000 $400,000 $- $9,000,000 $- $- $- $- $-
WBS A-066.54S001 Painting of Bridge No. NB-387, NB-389, NB-394, NB-506 $- $- $- $- $1,900,000 $- $- $- $- $-
WBS A-068.53S002 Replacement of Mainline Bridge No. NB-391 $100,000 $- $- $4,300,000 $30,000,000 $10,000,000 $1,500,000 $- $- $-
WBS A-070.26S004 Lehigh Tunnel In-Depth Inspection, 2009-10 $- $200,000 $300,000 $- $- $- $- $- $- $-
WBS A-074.27S001 Replacement of Lehigh & Pohopoco Bridges, NB-525, NB-526 $23,050,000 $55,500,000 $32,500,000 $15,100,000 $1,200,000 $- $- $- $- $-
WBS A-075.72S001 Redecking of Mahoning Valley Ramp Bridge No. NB-528 $100,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS A-076.09S001 Replacement of Mainline Bridge No. NB-531 $600,000 $600,000 $600,000 $100,000 $3,000,000 $6,000,000 $6,000,000 $- $- $-
WBS A-114.64S001 Replacement of Wyoming Valley Ramp Bridge No. NB-655 $400,000 $300,000 $300,000 $- $500,000 $5,000,000 $- $- $- $-
WBS A-115.33S001 Replacement of Overhead Bridge No. NB-659 $- $- $4,300,000 $- $- $- $- $- $- $-
WBS A-123.34S001 Replacement of Overhead Bridge No. NB-716 $5,000,000 $- $- $- $- $- $- $- $- $-
WBS A-128.87S001 Replacement of Overhead Bridge No. NB-736 $250,000 $200,000 $200,000 $- $- $2,000,000 $- $- $- $-
WBS DC-00000000000011 Collision Damage Repair to Bridge No. DB-141 $50,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS EN-00023 Misc. Tunnel Repairs - Systemwide $- $- $- $- $1,000,000 $1,100,000 $1,200,000 $1,300,000 $1,400,000 $1,500,000
WBS EN-00024 Study for Upgrades of the Commission's Tunnels $250,000 $300,000 $- $4,500,000 $4,500,000 $- $- $- $- $-
WBS EN-00050 Biennial Bridge Inspection Program Systemwide $- $400,000 $1,200,000 $1,200,000 $1,200,000 $1,300,000 $1,300,000 $1,300,000 $1,300,000 $1,300,000
WBS EN-00051 Annual Painting Program Systemwide $50,000 $50,000 $50,000 $50,000 $1,000,000 $1,000,000 $2,000,000 $2,000,000 $3,000,000 $3,000,000
WBS EN-00052 Misc. Bridge Repairs Systemwide (Open End Contracts) $- $- $1,200,000 $1,900,000 $1,900,000 $2,000,000 $2,000,000 $2,500,000 $3,000,000 $3,000,000
WBS EN-00053 Bridge Elimination Systemwide $50,000 $50,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000
WBS EN-00054 Bridge Rehabilitations Systemwide $250,000 $50,000 $500,000 $500,000 $500,000 $500,000 $24,300,000 $37,500,000 $42,800,000 $49,800,000
WBS EN-00056CY 2006-07 Biennial Bridge Inspection Program $10,000 $- $- $- $- $- $- $- $- $-
WBS EN-00058CY 2007 Misc.Bridge Repairs - Systemwide $100,000 $- $- $- $- $- $- $- $- $-
WBS EN-00059CY 2008 Misc. Bridge Repairs - Systemwide $1,900,000 $500,000 $- $- $- $- $- $- $- $-
WBS EN-00060CY 2008-09 Biennial Bridge Inspection Program $1,300,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS EN-00084CY 2009 Misc Bridge Repairs - Systemwide $50,000 $1,400,000 $500,000 $- $- $- $- $- $- $-
WBS T-013.21S001 Replacement of Mainline Bridge No. WB-211 $1,500,000 $2,000,000 $2,000,000 $2,000,000 $3,000,000 $27,000,000 $35,000,000 $37,000,000 $30,000,000 $23,000,000
WBS T-022.60S002 Replacement of Overhead Bridge No. WB-228 $300,000 $400,000 $300,000 $500,000 $4,000,000 $- $- $- $- $-
WBS T-029.72S002 Rehabilitation of Mainline Bridge No. WB-402 $600,000 $- $- $- $- $- $- $- $- $-
WBS T-048.00S002 Replacement of Allegheny River Bridge No. WB-443 $72,000,000 $41,200,000 $19,400,000 $- $- $- $- $- $- $-
WBS T-056.68S001 Redecking of Bridge No. WB-461 $200,000 $200,000 $1,795,000 $- $- $- $- $- $- $-
WBS T-059.58S001 Replacement of Bridge No. WB-500 $200,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS T-063.06S001 Replacement of Overhead Bridge No. WB-506 $300,000 $- $- $- $1,500,000 $3,000,000 $- $- $- $-
WBS T-067.05S002 Rehabilitation of Bridge No. B-458 $900,000 $- $- $- $- $- $- $- $- $-
WBS T-122.18S002 Allegheny Tunnel Project - Study Phase $- $- $- $- $200,000 $- $- $- $- $-
WBS T-122.18S005 Allegheny Tunnel Project - Design & Const. Phase $- $- $- $- $- $2,900,000 $2,900,000 $3,000,000 $22,900,000 $35,000,000
WBS T-122.18S008 Inspection and Rehabilitation of the Allegheny Tunnel--Design Phase $500,000 $1,300,000 $2,400,000 $- $- $- $- $- $- $-
WBS T-122.18S012 Allegheny Tunnel In-Depth Inspection, 2010-11 $- $- $100,000 $400,000 $- $- $- $- $- $-
WBS T-151.09S002 Replacement of Bridge No. B-443 $500,000 $4,000,000 $- $- $- $- $- $- $- $-
WBS T-153.06S002 Collision Damage Repairs to Bridge No. B-552 $500,000 $- $- $- $- $- $- $- $- $-
WBS T-171.85S001 Replacement of Mainline Bridge Nos.B-467A (EB/WB) $5,500,000 $- $- $- $- $- $- $- $- $-
WBS T-172.88S002 Replacement of Mainline Bridge Nos. B-521A (EB/WB) $200,000 $500,000 $500,000 $500,000 $2,000,000 $6,000,000 $1,000,000 $- $- $-
WBS T-184.66S001 Elimination of Bridge Nos. B-548, B-560W $1,000,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS T-186.20S002 Tuscarora Tunnel - In Depth Inspection, 2008-09 $400,000 $- $- $- $- $- $- $- $- $-
WBS T-186.20S004 Rehabilitation of th $- $300,000 $300,000 $2,900,000 $2,900,000 $- $- $- $- $-
WBS T-186.20S005 Tuscarora Tunnel In- $- $- $- $100,000 $400,000 $- $- $- $- $-
WBS T-197.20S001 Replacement of Overh $10,000 $- $- $- $- $- $- $- $- $-
WBS T-197.48S001 Blue Mountain and Ki $50,000 $- $- $- $- $- $- $- $- $-
WBS T-197.48S002 Blue Mountain/Kittat $100,000 $400,000 $- $- $- $- $- $- $- $-
WBS T-197.48S003 Replacement of the W $- $- $- $400,000 $1,000,000 $6,400,000 $6,500,000 $- $- $-
WBS T-197.48S004 Blue Mountain/Kittat $- $- $- $- $100,000 $500,000 $- $- $- $-
WBS T-245.72S001 Replacement of the S $2,000,000 $- $- $- $- $- $- $- $- $-
WBS T-251.08S002 Replacement of Swata $1,000,000 $- $- $10,000,000 $18,000,000 $9,000,000 $- $- $- $-
WBS T-255.66S002 D/B Superstructure R $100,000 $- $3,700,000 $- $- $- $- $- $- $-
WBS T-273.97S001 Rehabilitation of Ov $800,000 $2,370,000 $- $- $- $- $- $- $- $-
WBS T-282.88S001 Collision Damage Rep $350,000 $- $- $- $- $- $- $- $- $-
WBS T-315.87S001 Replacement of Bridg $100,000 $3,300,000 $- $- $- $- $- $- $- $-
WBS T-316.58S001 Replacement of Bridg $400,000 $500,000 $3,000,000 $- $- $- $- $- $- $-
WBS T-317.37S001 Replacement of Bridg $400,000 $50,000 $500,000 $3,000,000 $- $- $- $- $- $-
WBS T-342.75S001 Replacement of Mainl $500,000 $- $- $3,000,000 $9,000,000 $- $- $- $- $-
WBS T-357.32S001 Superstructure Rehab $50,000 $450,000 $- $- $- $- $- $- $- $-
                     
PTCCAP-01-03 Total Reconstruction $206,805,000 $130,000,000 $166,300,000 $239,900,000 $206,300,000 $198,000,000 $195,500,000 $201,000,000 $200,500,000 $200,500,000
WBS A-020.00T002 Total Reconstruction: MP A20 - A30 $15,800,000 $8,000,000 $29,000,000 $76,500,000 $82,500,000 $56,000,000 $41,000,000 $3,000,000 $- $-
WBS EN-00040 Total Reconstruction Program Design Management $3,500,000 $2,500,000 $2,000,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000
WBS EN-00048 Total Reconstruction - Systemwide $- $- $- $60,400,000 $95,300,000 $124,500,000 $135,500,000 $185,400,000 $190,100,000 $190,600,000
WBS T-000.00T001 Total Reconstruction MP 0-10 (Constr. Phase) $30,400,000 $3,000,000 $100,000 $- $- $- $- $- $- $-
WBS T-031.20T001 Total Reconstruction MP 31.2 - 40 $1,000,000 $- $- $- $- $- $- $- $- $-
WBS T-031.20T002 Ultimate Warrendale (Const. Phase) $- $- $- $- $- $6,000,000 $7,000,000 $- $- $-
WBS T-031.20T003 Total Reconstruction MP 31 - 38 (Const. Phase) $5,505,000 $15,000,000 $52,000,000 $51,000,000 $24,000,000 $- $- $- $- $-
WBS T-040.00T001 Total Reconstruction MP 40 - 48 (Design Phase) $1,300,000 $2,400,000 $1,800,000 $- $2,000,000 $3,000,000 $2,000,000 $1,000,000 $- $-
WBS T-067.00T001 Total Reconstruction MP 67 - 75 (Design Phase) $2,000,000 $- $- $- $- $- $- $- $- $-
WBS T-067.00T003 Total Reconstruction MP 67 - 75 (Const. Phase) $31,600,000 $40,200,000 $45,000,000 $36,000,000 $- $- $- $- $- $-
WBS T-099.00T002 Total Reconstruction MP 99 - 109 (Design Phase) $800,000 $- $2,500,000 $2,000,000 $1,000,000 $- $- $- $- $-
WBS T-123.00T002 Design /Build Project for the Relocation of Allegheny Mountain WB Lanes, MP 123-129 $14,000,000 $- $- $- $- $- $- $- $- $-
WBS T-129.00T001 Total Reconstruction MP 128 - 134 (Design Phase) $700,000 $500,000 $- $- $- $2,500,000 $2,500,000 $2,500,000 $- $-
WBS T-138.00T001 Total Reconstruction MP 138 - 140 (Design Phase) $- $- $- $- $- $- $- $1,600,000 $3,000,000 $3,000,000
WBS T-149.50T002 Total Reconstruction MP 149.5 - 155.5 (Design Phase) $1,500,000 $1,000,000 $1,000,000 $- $- $2,500,000 $2,500,000 $2,000,000 $- $-
WBS T-179.50T001 Total Reconstruction MP 179.5 - 186 (Design Phase) $- $- $- $- $- $- $- $1,600,000 $2,400,000 $1,900,000
WBS T-199.00T002 Total Reconstruction MP 199 - 214 (Design Phase) $3,000,000 $2,000,000 $2,000,000 $1,000,000 $- $- $- $- $- $-
WBS T-199.00T005 Total Reconstruction MP 199 - 202 (Const. Phase) $2,600,000 $13,000,000 $21,000,000 $10,500,000 $- $- $- $- $- $-
WBS T-211.00T001 Total Reconstruction MP 211 - 215 (Design Phase) $42,000,000 $23,000,000 $- $- $- $- $- $- $- $-
WBS T-214.00T002 Total Reconstruction MP 214 - 227 (Design Phase) $3,000,000 $2,000,000 $2,000,000 $1,000,000 $- $- $- $- $- $-
WBS T-215.00T001 Total Reconstruction MP 215 - 220 (Const. Phase) $2,100,000 $5,600,000 $3,700,000 $- $- $- $- $- $- $-
WBS T-220.00T001 Total Reconstruction MP 220 - 227 (Const. Phase) Carlisle I/C $3,800,000 $7,800,000 $2,400,000 $- $- $- $- $- $- $-
WBS T-242.00T002 Total Reconstruction MP 242 - 245 (Design Phase) $800,000 $- $- $- $- $2,000,000 $2,000,000 $- $- $-
WBS T-312.00T003 Total Reconstruction MP 312 - 319 (Design Phase) $- $- $- $- $- $- $1,500,000 $2,400,000 $3,500,000 $3,500,000
WBS T-319.00T001 Total Reconstruction MP 319 - 326 (Design Phase) $6,900,000 $4,000,000 $1,800,000 $- $- $- $- $- $- $-
WBS T-326.20T001 Total Reconstruction MP 326 - 333 (Const. Phase) $34,500,000 $- $- $- $- $- $- $- $- $-
                     
PTCCAP-01-04 Slip Ramp/Interchange $26,080,000 $21,150,000 $63,250,000 $64,985,000 $54,560,000 $62,725,000 $55,390,000 $68,550,000 $48,000,000 $35,600,000
WBS A-075.86P002 Rehabilitation of Mahoning Valley I/C $- $- $- $200,000 $1,000,000 $1,000,000 $1,500,000 $10,000,000 $15,000,000 $2,000,000
WBS A-087.00P001 Slip Ramp Interchange, MP A87,Route 9 $1,000,000 $3,000,000 $10,000,000 $8,000,000 $- $- $- $- $- $-
WBS A-105.44P002 Rehabilitation of Wilkes Barre I/C $- $- $200,000 $1,000,000 $1,000,000 $1,500,000 $10,000,000 $14,000,000 $2,000,000 $-
WBS A-130.64P001 Clark's Summit Toll Plaza Modifications $6,000,000 $- $- $- $- $- $- $- $- $-
WBS EN-00061 Slip Ramp Study & Design $50,000 $50,000 $50,000 $50,000 $500,000 $500,000 $500,000 $1,000,000 $1,000,000 $1,000,000
WBS T-056.44P001 Rehabilitation of Pittsburgh I/C $200,000 $1,000,000 $1,500,000 $1,000,000 $15,000,000 $12,000,000 $- $- $- $-
WBS T-075.39P001 Rehabilitation of New Stanton I/C $- $200,000 $1,000,000 $1,000,000 $1,500,000 $10,000,000 $13,000,000 $5,000,000 $- $-
WBS T-080.00P001 Slip Ramp Interchange MP 80 $50,000 $- $- $- $- $- $- $- $- $-
WBS T-236.22P001 Rehabilitation and Expansion of Gettysburg I/C $10,000 $- $- $- $- $- $- $- $- $-
WBS T-247.38P001 Rehabilitation of Harrisburg East I/C $10,000 $- $- $- $- $- $- $- $- $-
WBS T-266.45P002 Rehabilitation and Expansion of Lebanon-Lancaster I/C $10,000 $- $- $- $- $- $- $- $- $-
WBS T-319.30P001 Slip Ramp Interchange, MP 319, Route 29 $100,000 $3,000,000 $40,000,000 $27,000,000 $2,000,000 $- $- $- $- $-
WBS T-331.60P001 Lafayette Street Slip Ramps MP 331.6 $150,000 $1,000,000 $1,000,000 $3,000,000 $18,130,000 $19,800,000 $19,050,000 $13,020,000 $- $-
WBS T-351.90P001 Bensalem Township Slip Ramps @ South Neshaminy $6,500,000 $1,900,000 $- $- $- $- $- $- $- $-
WBS T-355.00P001 I-95 Interchange $12,000,000 $11,000,000 $9,500,000 $23,735,000 $15,430,000 $17,925,000 $11,340,000 $25,530,000 $30,000,000 $32,600,000
                     
PTCCAP-01-05 Highway Miscellaneous $11,750,000 $7,630,000 $5,455,000 $5,785,000 $6,650,000 $6,875,000 $7,210,000 $7,550,000 $7,900,000 $8,100,000
WBS A-055.90M001 Allentown Service Plaza Parking Area Improvements $2,600,000 $- $- $- $- $- $- $- $- $-
WBS EN-00026 Rock Cuts Systemwide $100,000 $100,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000
WBS EN-00027 Major Guide Sign Update/Replacement Systemwide $2,900,000 $1,900,000 $50,000 $50,000 $300,000 $300,000 $350,000 $350,000 $400,000 $400,000
WBS EN-00031 Systemwide Traffic Study $400,000 $50,000 $50,000 $50,000 $300,000 $300,000 $350,000 $350,000 $400,000 $400,000
WBS EN-00032 Radio Tower Access Road $50,000 $50,000 $50,000 $50,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000
WBS EN-00034 Consulting Engineering Services $2,800,000 $2,900,000 $2,900,000 $3,000,000 $3,000,000 $3,100,000 $3,200,000 $3,300,000 $3,400,000 $3,500,000
WBS EN-00035 Open End Engineering Services $950,000 $1,000,000 $1,000,000 $1,000,000 $1,100,000 $1,200,000 $1,300,000 $1,400,000 $1,500,000 $1,600,000
WBS EN-00037 Turnpike Coordination on PaDOT Projects involving Turnpike Infrastructure $100,000 $100,000 $100,000 $100,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
WBS EN-00046 Warranty Activities for Design/Build Projects $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000 $100,000
WBS EN-00062 Project Management/Cost Control and Construction Documentation System $250,000 $- $- $- $- $- $- $- $- $-
WBS EN-00063 Electronic Bidding System for Construction Contracts $400,000 $420,000 $445,000 $475,000 $500,000 $525,000 $560,000 $600,000 $650,000 $650,000
WBS EN-00064 Design/Construction Audit Services $150,000 $100,000 $- $- $- $- $- $- $- $-
WBS EN-00089BMP (Stormwater) Maintenance Systemwide $50,000 $200,000 $200,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
WBS EN-00092 Engineering Automation/Pavement Management $900,000 $710,000 $310,000 $210,000 $300,000 $300,000 $300,000 $400,000 $400,000 $400,000
WBS T-112.37M001 Auxiliary Truck Park $- $- $- $- $- $- $- $- $- $-
                     
PTCCAP-02 Facilities Program $33,400,000 $43,620,000 $34,000,000 $34,700,000 $34,700,000 $33,100,000 $38,000,000 $38,600,000 $39,000,000 $37,000,000
PTCCAP-02-01 Re-capitalization Pr $2,870,000 $2,000,000 $11,600,000 $21,500,000 $16,100,000 $14,000,000 $7,200,000 $16,900,000 $24,300,000 $22,300,000
WBS A-094.64F001 Recapitalization--Re $400,000 $- $- $- $- $- $- $- $- $-
WBS EN-00004 V-000.00F057 - Recap $- $- $- $- $- $- $7,200,000 $16,900,000 $24,300,000 $22,300,000
WBS EN-00008 V-000.00F062 - Recap $250,000 $- $- $- $- $- $- $- $- $-
WBS EN-00017 V-000.00F074 - Recap $320,000 $- $- $- $- $- $- $- $- $-
WBS EN-00018 V-000.00F075 - Recap $400,000 $500,000 $600,000 $- $- $- $- $- $- $-
WBS EN-00025 V-000.00P012 - Recap $500,000 $1,000,000 $500,000 $- $- $- $- $- $- $-
WBS T-039.59F001 Recapitalization--Re $- $- $- $1,500,000 $16,100,000 $14,000,000 $- $- $- $-
Recapitalization--So $1,000,000 $500,000 $10,500,000 $20,000,000 $- $- $- $- $- $-
                     
PTCCAP-02-02 Sustainment Program $9,280,000 $7,600,000 $7,700,000 $9,500,000 $9,700,000 $10,700,000 $11,700,000 $11,700,000 $11,700,000 $11,700,000
WBS A-070.07F005 Sustainment--Lehigh $400,000 $- $- $- $- $- $- $- $- $-
WBS EN-00001 V-000.00F054 - Susta $400,000 $400,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
WBS EN-00003 V-000.00F056 - Susta $- $- $- $1,800,000 $2,000,000 $2,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000
WBS EN-00009 V-000.00F063 - Susta $900,000 $900,000 $900,000 $900,000 $900,000 $900,000 $900,000 $900,000 $900,000 $900,000
WBS EN-00011 V-000.00F067 - Susta $- $6,000,000 $6,000,000 $6,000,000 $6,000,000 $7,000,000 $7,000,000 $7,000,000 $7,000,000 $7,000,000
WBS EN-00012 V-000.00F069 - Susta $- $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000
WBS EN-00015 V-000.00F072 - Susta $- $- $- $- $- $- $- $- $- $-
WBS EN-00021 V-000.00F078 - Susta $1,600,000 $- $- $- $- $- $- $- $- $-
WBS EN-00022 V-000.00F079 - Susta $30,000 $- $- $- $- $- $- $- $- $-
WBS EN-00085 Sustainment General $5,000,000 $- $- $- $- $- $- $- $- $-
WBS EN-00086 Sustainment--Furnitu $300,000 $- $- $- $- $- $- $- $- $-
WBS T-011.84F002 Sustainment--Homewoo $650,000 $- $- $- $- $- $- $- $- $-
WBS T-197.48F001 Sustainment--Blue/Ki $- $- $- $- $- $- $- $- $- $-
                     
PTCCAP-02-03 Compliance Program $3,720,000 $1,700,000 $1,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000
WBS EN-00002 V-000.00F055 - Compl $- $- $- $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
WBS EN-00010 V-000.00F065 - Compl $- $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
WBS EN-00013 V-000.00F070 - Compl $- $- $- $- $- $- $- $- $- $-
WBS EN-00014 V-000.00F071 - Compl $2,000,000 $700,000 $- $- $- $- $- $- $- $-
WBS EN-00020 V-000.00F077 - Compl $400,000 $- $- $- $- $- $- $- $- $-
WBS EN-00087 Compliance General F $1,000,000 $- $- $- $- $- $- $- $- $-
WBS T-185.95 F002Compliance--Burnt Ca $320,000 $- $- $- $- $- $- $- $- $-
                     
PTCCAP-02-04 New Initiative Progr $17,530,000 $32,320,000 $13,700,000 $1,700,000 $6,900,000 $6,400,000 $17,100,000 $8,000,000 $1,000,000 $1,000,000
WBS A-070.07F006 New Initiative--Cons $- $- $- $300,000 $400,000 $3,900,000 $3,100,000 $- $- $-
WBS EN-00005 V-000.00F058 - New I $- $- $- $- $- $- $- $1,000,000 $1,000,000 $1,000,000
WBS EN-00019 V-000.00F076 - New I $30,000 $660,000 $- $- $- $- $- $- $- $-
WBS T-154.42F003 New Initiative--Cons $1,800,000 $1,700,000 $- $- $- $- $- $- $- $-
WBS T-214.26F003 New Initiative -- Ne $- $60,000 $600,000 $- $- $- $- $- $- $-
WBS T-243.85F003 New Initiative -- Ne $100,000 $900,000 $- $- $- $- $- $- $- $-
WBS T-247.38F003 New Initiative--Relo $12,000,000 $12,000,000 $- $- $- $- $- $- $- $-
WBS T-288.33F001 New Initiative--Dist $- $- $- $600,000 $6,000,000 $1,000,000 $- $- $- $-
WBS T-288.33F003 New Initiative -- Bo $- $- $100,000 $800,000 $- $- $- $- $- $-
WBS T-316.26F001 New Initiative--Relo $- $- $- $- $500,000 $1,500,000 $14,000,000 $7,000,000 $- $-
WBS T-333.59F001 New Initiative--Relo $3,600,000 $17,000,000 $13,000,000 $- $- $- $- $- $- $-
                     
PTCCAP-03 Fleet Equipment Prog $11,100,000 $7,500,000 $8,500,000 $9,300,000 $10,800,000 $11,900,000 $8,000,000 $7,400,000 $8,000,000 $8,000,000
                     
PTCCAP-04 Technology Program $36,163,000 $22,140,000 $29,790,000 $19,440,000 $16,900,000 $34,000,000 $23,100,000 $12,000,000 $12,000,000 $10,000,000
PTCCAP-04-01 Functional Business Software $18,525,000 $5,390,000 $16,550,000 $12,520,000 $12,700,000 $22,000,000 $19,050,000 $8,150,000 $8,250,000 $8,450,000
WBS IT-00019 ENTERPRISE RESOURCE PLANNING SYSTEM $8,225,000 $- $- $- $- $- $- $- $- $-
WBS IT-00020 ENTERPRISE TECHNOLOGY PROJECTS $4,225,000 $4,090,000 $15,850,000 $11,820,000 $11,000,000 $19,800,000 $19,050,000 $8,150,000 $8,250,000 $8,450,000
WBS IT-00021 PROJECT COLLABORATOIN TOOL $1,300,000 $1,300,000 $700,000 $700,000 $1,700,000 $2,200,000 $- $- $- $-
WBS IT-00026 PROJECT MANAGEMENT TRAINING PROGRAM $200,000 $- $- $- $- $- $- $- $- $-
WBS IT-00034 Strategic Sourcing Concepts Services $300,000 $- $- $- $- $- $- $- $- $-
WBS IT-00036 SAP Enterprise Solution - Enhancements $3,775,000 $- $- $- $- $- $- $- $- $-
WBS IT-00037 Enterprise Scanning $500,000 $- $- $- $- $- $- $- $- $-
                     
PTCCAP-04-02 Infrastructure HW / SW $7,833,000 $12,000,000 $9,840,000 $5,120,000 $3,200,000 $12,000,000 $4,050,000 $3,850,000 $3,750,000 $1,550,000
WBS IT-00009 COMMUNICATIONS RADIO REPLACEMENT $100,000 $100,000 $400,000 $600,000 $600,000 $600,000 $600,000 $600,000 $600,000 $600,000
WBS IT-00010 FIELD UPGRADES - TELEPHONE SYSTEMS AND PATRON INTERCOM REPLACEMENTS $100,000 $100,000 $240,000 $240,000 $440,000 $240,000 $440,000 $240,000 $440,000 $240,000
WBS IT-00011 LAST MILE CONNECTIVITY $- $- $240,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000
WBS IT-00012 CALL BOX REFURBISHMENT $- $- $160,000 $160,000 $160,000 $160,000 $160,000 $160,000 $160,000 $160,000
WBS IT-00013 ITS ENHANCEMENT PROJECTS PHASE 4 THRU 6 $3,176,444 $5,300,000 $1,900,000 $- $- $- $- $- $- $-
WBS IT-00014 ITS SOFTWARE ENHANCEMENT PHASE 7 & 8 $66,556 $- $- $- $- $- $- $- $- $-
WBS IT-00016 ITS INSTALLED BASE UPGRADE, RETROFIT AND REPAIR $- $- $450,000 $450,000 $450,000 $450,000 $300,000 $300,000 $- $-
WBS IT-00017 TRAFFIC FLOW DATA SERVICE CONTRACT $- $- $2,300,000 $2,300,000 $- $- $- $- $- $-
WBS IT-00022 TECHNOLOGY ASSETS UPGRADES, NEW PURCHASES $- $2,500,000 $2,250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000 $250,000
WBS IT-00023 Z-000.00O014 - INFRA $1,500,000 $2,000,000 $1,000,000 $820,000 $1,000,000 $10,000,000 $2,000,000 $2,000,000 $2,000,000 $-
WBS IT-00024 Z-000.00C070 - COMPU $2,000,000 $1,000,000 $- $- $- $- $- $- $- $-
WBS IT-00027 Z-000.00C071 - HIGHW $400,000 $1,000,000 $900,000 $- $- $- $- $- $- $-
WBS IT-00038 Wireless Telecommuni $490,000 $- $- $- $- $- $- $- $- $-
                     
PTCCAP-04-03 Toll Collect / Operations $9,805,000 $4,750,000 $3,400,000 $1,800,000 $1,000,000 $- $- $- $- $-
WBS IT-00001 Z-000.00A004 - ENHAN $500,000 $- $- $- $- $- $- $- $- $-
WBS IT-00002 Z-000.00A005 - ETC E $1,000,000 $- $- $- $- $- $- $- $- $-
WBS IT-00003 Z-000.00A017 - ADDIT $1,500,000 $2,000,000 $1,500,000 $- $- $- $- $- $- $-
WBS IT-00004 Z-000.00A019 - ETC I $3,000,000 $- $- $- $- $- $- $- $- $-
WBS IT-00005 Z-000.00A021 - ETC S $1,000,000 $750,000 $750,000 $750,000 $- $- $- $- $- $-
WBS IT-00007 Z-000.00A027 - DIGIT $1,505,000 $900,000 $- $- $- $- $- $- $- $-
WBS IT-00008 Z-000.00A028 - TOLL $800,000 $800,000 $1,000,000 $1,000,000 $1,000,000 $- $- $- $- $-
WBS IT-00025 Z-000.00A029 - BUSIN $500,000 $300,000 $150,000 $50,000 $- $- $- $- $- $-